• Latest Local News
Pit Bull kills dog, injures elderly woman
Pit Bull kills dog, injures woman

A pit bull is in the custody of Bernalillo County Animal …

Parts of I-40 closed after fatal rollover
Parts of I-40 closed after fatal crash

The Albuquerque police department responded to I-40 westbound …

Humans, drought behind record wildfires
Humans, drought behind record wildfires

With last year's record-breaking Las Conchas fire and this …

Evening Webcast: May 29, 2012
Evening Webcast: May 29, 2012

Kristen Van Dyke with the latest weather forecast and Dianne …

Two overnight fires caused by arson
Two overnight fires caused by arson

The Albuquerque fire department says two fires in a span of a …

Advertisement

Congress yanks cash away from New Mexico nuke lab

Updated: Saturday, 24 Dec 2011, 4:56 PM MST
Published : Saturday, 24 Dec 2011, 4:56 PM MST

LOS ALAMOS, N.M. (AP) - It will be about a year before construction can start on a new plutonium laboratory at Los Alamos after Congress pulled back funding for the project and restricted how the money can be spent.

The Albuquerque Journal reports the congressional action also raises questions about the long-term prospects for the new Chemistry and Metallurgy Research Replacement Nuclear Facility.

The final congressional report said that no construction activities are funded for the CMRR-Nuclear Facility during Fiscal Year 2012.

Lab and federal documents suggest the construction to be deferred this year includes preliminary excavation work, the start of construction on a concrete plant for the massive structure and erection of the project's construction management trailers.

In all, the lab has issued at least 45 notices to potential bidders regarding possible contracting opportunities on the project, according to a review by Trish Williams-Mello of the Los Alamos Study Group, which opposes the project.

In addition to construction-related opportunities, the announcements include plans for acquiring equipment for the building for fire safety systems and guard facilities.

While cutting from the administration's funding request for the nuclear facility, Congress gave full funding to a similar multibillion dollar project being built in Tennessee for work on uranium nuclear weapon parts.

That led some observers to speculate that Congress may be setting the stage for further delays in the Los Alamos plutonium lab because of concerns the agency cannot afford to work on both large projects simultaneously.

"Simultaneous construction of these projects is considered difficult to impossible by many in government," Greg Mello, of the Los Alamos Study Group, wrote in a letter to supporters this week. "Up to now at least, CMRR-NF has been the National Nuclear Security Administration's highest priority infrastructure project. Congress, authorizers and appropriators alike, and in both the House and Senate, evidently think differently, at least for the time being." The Los Alamos nuclear facility has been plagued by delays and rising costs. Even before the congressional vote to delay construction, plans called for completion in 2023, more than a decade behind the original schedule when the project was launched.

___

Information from: Albuquerque Journal


Photos: Olympic portraits

Photos from the 2012 Team USA Media Summit.

Photos: Another fatal quake rocks Italy

Residents had just been taking tentative steps toward resuming normal life when …

Peterson Golden Spikes semifinalist

Lobos sophomore third baseman DJ Peterson is a semifinalist for the Golden …

Tapia died on anniv. of mom's death

To just about everyone who met Johnny Tapia, he was a friend, always greeting …

John's Wednesday Morning Forecast

Watch the complete New Mexico weather forecast & get latest updates from the

Current wind speeds, gusts, forecast

Latest conditions and forecast for Albuquerque and New Mexico winds.

Share |

Report It to KRQE News 13

Advertisement
  • Current Conditions - Statewide
Advertisement

Advertisement